Time needed to qualify a backup
Production stoppages, longer lead times and specification changes can expose dependence on one source. Before relying on an alternative, establish that it meets the quality specification and works in the intended process.
Stock gap during a 45-day lead time
At 500 kg per 30-day month, use is about 16.7 kg/day. A 300 kg stock covers roughly 18 days. If the next shipment is 45 days away and no delivery intervenes, the gap is about 450 kg. Include qualification and shipping time in the alternative supply plan.